【产通社,3月17日讯】TDK Corporation官网消息,受地震以及电力中断影响,其部分部分生产设施曾经停止运营,目前大部分设施正在恢复生产。具体情况如下: TDK Group sites in Kanto District under the service by Tokyo Electric Power Company JAPAN Sites Location Products Status as of March 15 1 TDK Corporation Narita Plant Narita-city, Chiba metal magnets The production lines are ready for the production, which may, however, be affected by the rolling blackout planned by the electricity supply company. 2 TDK Corporation Kofu Plant Minami-Alps-city, Yamanashi thin-film devices, silicon devices The production lines are ready for the production, which may, however, be affected by the rolling blackout planned by the electricity supply company. 3 TDK Corporation Technical Center Ichikawa-city, Chiba R&D base The plant is in the operation, which may, however, be affected by the rolling blackout planned by the electricity supply company. 4 Media Technology Corporation Chuo-city, Yamanashi data storage tapes The production lines are ready for the production, which may, however, be affected by the rolling blackout planned by the electricity supply company. 5 TDK Micro Device Corporation Kitaibaraki-city, Ibaraki organic EL displays The plant is not in the operation, the damaged parts being repaired. TDK Group sites in Tohoku district under the service by Tohoku Electric Power Company JAPAN Sites Location Products Status as of March 15 1 TDK Corporation Akita Plant Nikaho-city, Akita various electronic materials The production lines are ready for the production, which may, however, be affected by the rolling blackout planned by the electricity supply company. 2 TDK-EPC Corporation Chokai Plant Nikaho-city, Akita ferrite cores The production lines are ready for the production, which may, however, be affected by the rolling blackout planned by the electricity supply company. 3 TDK Corporation Kisakata Plant Nikaho-city, Akita various electronic components development The plant is in the operation, which may, however, be affected by the rolling blackout planned by the electricity supply company. 4 TDK Corporation Inakura Plant Nikaho-city, Akita ferrite cores The production lines are ready for the production, which may, however, be affected by the rolling blackout planned by the electricity supply company. 5 TDK Corporation Hirasawa Plant Nikaho-city, Akita R&D base The plant is in the operation, which may, however, be affected by the rolling blackout planned by the electricity supply company. 6 TDK-MCC Coporation Akita Plant Nikaho-city, Akita capacitors The production lines are ready for the production, which may, however, be affected by the rolling blackout planned by the electricity supply company. 7 TDK-MCC Corporation Kitakami Plant Kitakami-city, Iwate capacitors The plant has recovered from the damage and is ready for the production as of today (Mar. 15). The production, however, may be affected by the rolling blackout planned by the electricity supply company. 8 TDK-MCC Corporation Honjo Plant Yurihonjo-city, Akita capacitors The production lines are ready for the production, which may, however, be affected by the rolling blackout planned by the electricity supply company. 9 TDK-MCC Corporation Kisakata Plant Nikaho-city, Akita capacitors The plant has re-started the operation, which may, however, be affected by the rolling blackout planned by the electricity supply company. 10 TDK Ugo Corporation Yurihonjo-city, Akita coils, high-frequency components The production lines are ready for the production, which may, however, be affected by the rolling blackout planned by the electricity supply company. 11 TDK Ugo Corporation Konoura Plant Nikaho-city, Akita coils, high-frequency components The plant has re-started the operation, which may, however, be affected by the rolling blackout planned by the electricity supply company. 12 TDK Ugo Corporation Yuzawa Plant Yuzawa-city, Akita coils, high-frequency components The plant has re-started the operation, which may, however, be affected by the rolling blackout planned by the electricity supply company. 13 TDK Ugo Corporation Iwaki Plant Yurihonjo-city, Akita coils, high-frequency components The plant has re-started the operation, which may, however, be affected by the rolling blackout planned by the electricity supply company. 14 TDK Yurihonjo Corporation Honjo Plant Yurihonjo-city, Akita power supplies The plant has re-started the operation, which may, however, be affected by the rolling blackout planned by the electricity supply company. 15 TDK Yurihonjo Corporation Yashima Plant Yurihonjo-city, Akita sensors The plant has re-started the operation, which may, however, be affected by the rolling blackout planned by the electricity supply company. 16 TDK Ujo Corporation Katagami-city, Akita capacitors The plant has re-started the operation, which may, however, be affected by the rolling blackout planned by the electricity supply company. 17 TDK Shonai Corporation Tsuruoka-city, Yamagata coils, transformers, power supplies, sensors The plant is in the operation, which may, however, be affected by the rolling blackout planned by the electricity supply company. 18 TDK Shonai Corporation Sakata Plant Sakata-city, Yamagata coils, transformers, power supplies, sensors The plant has re-started the operation, which may, however, be affected by the rolling blackout planned by the electricity supply company. 19 TDK Shonai Corporation Yuza Plant Yuza-machi Akumi-gun, Yamagata coils, transformers, power supplies, sensors The plant has re-started the operation, which may, however, be affected by the rolling blackout planned by the electricity supply company. TDK Group sites in Kanto District under the service by Tokyo Electric Power Company JAPAN Sites Location Products Status as of March 17 1 TDK Corporation Narita Plant Narita-city, Chiba metal magnets The production lines are ready for the production, which, however, have been affected by the rolling blackout planned by the electricity supply company. 2 TDK Corporation Kofu Plant Minami-Alps-city, Yamanashi thin-film devices, silicon devices The plant has re-started the operation, which, however, has been affected by the rolling blackout planned by the electricity supply company. 3 TDK Corporation Technical Center Ichikawa-city, Chiba R&D base The plant is in the operation, which, however, has been affected by the rolling blackout planned by the electricity supply company. 4 Media Technology Corporation Chuo-city, Yamanashi data storage tapes The plant has re-started the operation, which, however, has been affected by the rolling blackout planned by the electricity supply company. 5 TDK Micro Device Corporation Kitaibaraki-city, Ibaraki organic EL displays The plant is not in the operation, the damaged parts being repaired. Besides, it has been affected by the rolling blackout planned by the electricity supply company. 查询进一步信息,请访问http://www.tdk.com/#。 (完)
|